- Stage
- Application filed, hearing scheduled
- Town
- Voorhees Township
- County
- Camden County
- Type
- Commercial
- Latest step
- Jun 24, 2026
The project
A four megawatt DC community solar array across about 13.5 acres of a roughly 18 acre township owned site at 300 Centennial Boulevard, the former Buzby Brothers Landfill. The panels sit on precast ballast blocks on top of the landfill cap rather than piercing it, and stand eight feet tall.
Where it is
The project is on part of this land. Which part has not been made public.
Steps so far
- Approved
Preliminary and final major site plan approved with bulk variances and design waivers, nine ayes and no nays, on application PC#26-011, subject to six conditions.
Source: Voorhees Township Planning Board · Read the document - Filed
Voorhees Township Planning Board agenda lists the preliminary and final major site plan (PC#26-011) as new business.
Source: Voorhees Township Planning Board · Read the document
Each step is our own summary of a public board or agency document, linked where the document is online. A project's status can change at the next meeting. General information, not legal advice. Justin Kelly, NJ Real Estate Broker-Salesperson, License #1540232. Brokered with OMNI Real Estate Professionals. Equal Housing Opportunity.