- Filed
- Hearing held
- Approved
- State permits pending
- Under construction
- Fully built
No new board documents in about 90 days. The stage shown is the last step it reached.
- Stage
- Hearing held, no final approval yet
- Town
- Oldmans Township
- County
- Salem County
- Type
- Commercial
- Size
- 492,900 sq ft
- Latest step
- Jul 21, 2025
The project
A 400,000 square foot speculative warehouse on about 57 vacant acres off Straughns Mill Road, made up of 20,000 square feet of office and 380,000 square feet of warehouse. The board was told the warehouse is a permitted use there and that the applicant would be asking for a height variance to 65 feet.
Where it is
Steps so far
- Hearing held
The board deemed the application complete nine votes to none after the engineer reviewed his completeness letter and agreed to the eleven waivers requested. No approval was voted.
Source: Oldmans Township Planning Board · Read the document - Hearing held
The Oldmans Township Planning Board deemed the preliminary major subdivision and preliminary site plan complete, heard testimony, and continued the hearing to July 21, 2025.
Source: Oldmans Township Planning Board · Read the document - Hearing held
The Oldmans Township Planning Board granted preliminary major subdivision and preliminary site plan approval, 9-0, with conditions.
Source: Oldmans Township Planning Board · Read the document
Each step is our own summary of a public board or agency document, linked where the document is online. A project's status can change at the next meeting. General information, not legal advice. Justin Kelly, NJ Real Estate Broker-Salesperson, License #1540232. Brokered with OMNI Real Estate Professionals. Equal Housing Opportunity.