1. Filed
  2. Hearing held
  3. Approved
  4. State permits pending
  5. Under construction
  6. Fully built
Stage
Hearing held, no final approval yet
Town
Monroe Township
County
Gloucester County
Type
Commercial
Size
1,600,000 sq ft
Latest step
Aug 31, 2026

The project

A redevelopment area that named data centres as a permitted use in 2025, until the township adopted ordinances taking that use back out and barring data centres township wide.

Where it is

Steps so far

  1. Hearing held

    Pinelands Commission minutes report the Monroe Planning Board granted preliminary site plan approval on January 8 for a 1.6-million-square-foot warehouse and distribution centre in the Hexa Builders Redevelopment Area.

    Source: New Jersey Pinelands Commission · Read the document
  2. Filed

    Pinelands Commission minutes report a proposed ordinance on data centre standards for the Hexa Builders plan was on the township council agenda but not introduced, and no data centre application is before the Commission.

    Source: New Jersey Pinelands Commission · Read the document
  3. Hearing held

    Monroe Township's planner told the commission's policy and implementation committee that the township had adopted two ordinances banning data centres in the township and removing data centres as a permitted use on the Hexa-Builders site. He said the site is not near the Hightop Redevelopment Area, answering a commissioner's question about the two competing for water.

    Source: New Jersey Pinelands Commission · Read the document
  4. Hearing held

    Pinelands Commission minutes report staff found ordinances from Monroe, Pemberton and Waterford prohibiting data centres raise no substantial issue.

    Source: New Jersey Pinelands Commission · Read the document
  5. Filed

    A Hexa Builders, LLC site plan, file MO-0511Sp, went to the county review committee listed as '1,500,000 Commercial', with no unit printed, and county review was waived.

    Source: Gloucester County Land Development Review Committee · Read the document
  6. Filed

    Pinelands Commission minutes report the applicant asked to build a data centre and a warehouse instead of two warehouses; staff required an amended Certificate of Filing, now under review, and said there is no right of appeal from that decision.

    Source: New Jersey Pinelands Commission · Read the document
  7. Filed

    Pinelands Commission minutes report the amended warehouse and data centre application is under review, that the current redevelopment plan prohibits data centres, and that Hexa Builders filed a notice of appeal with the Appellate Division.

    Source: New Jersey Pinelands Commission · Read the document
  8. Hearing held

    The Land Use Programs Office reported that two further Monroe Township ordinances were reviewed and found to raise no substantial issue with the Comprehensive Management Plan: O:31-2026, which bars on-site generators as a primary power source when fuelled by fossil fuels, nuclear materials, petroleum-based products or other combustible materials except in limited circumstances and requires power to come from the regional grid, zero-emission sources or clean generators, with enforcement provisions and penalties; and O:30-2026, which defines and expressly prohibits detention, correctional and carceral facilities throughout the township.

    Source: New Jersey Pinelands Commission · Read the document
Back to the development map

Each step is our own summary of a public board or agency document, linked where the document is online. A project's status can change at the next meeting. General information, not legal advice. Justin Kelly, NJ Real Estate Broker-Salesperson, License #1540232. Brokered with OMNI Real Estate Professionals. Equal Housing Opportunity.